Aluminum Alloy Permanent Mold Gravity Casting: Temperature & Velocity Control (Mainly for A356/A357)
Core principles: Match temperature to wall thickness; aim for smooth laminar flow in speed control; avoid air entrapment, oxidation, cold shuts, and shrinkage cavities. Temperature involves two systems: molten aluminum pouring temperature and mold temperature. Speed refers to the ingate filling linear velocity / total pouring time.
I. Temperature Control
- Molten aluminum pouring temperature (measured temperature at tap-out and at the ingate; thermocouple / infrared temperature measurement)
Liquidus: A356 is approximately 610°C. The pouring temperature is generally 70–100°C above the liquidus.
- Thin-wall parts (<4 mm, complex cavities): 730–750°C to ensure fluidity and prevent cold shuts and misruns.
- Normal wall thickness (4–15 mm, housings, brackets): 710–730°C (most commonly used).
- Thick sections (>15 mm, valve bodies, wheel hubs, etc.): 690–710°C. Too high a temperature will aggravate gas absorption, oxidation, coarse grains, microshrinkage, and hot tearing.
- Tolerance: after production is stable, control within ±5°C; if transfer time is long (ladling, transport), increase appropriately by 5–10°C to compensate for temperature drop.
✅ Defects caused by excessively high temperature: gas porosity, oxidation inclusions, shrinkage cavities, coarse grains, mold burnout, hot cracks.
✅ Defects caused by excessively low temperature: cold shuts, misruns, flow lines, inclusions.
Melting furnace temperature: 20–30°C higher than the pouring temperature to allow for temperature drop during ladling and transport. Degassing + refining + grain refinement must be provided as supporting processes; high-temperature molten aluminum readily absorbs hydrogen.
- Mold (permanent mold) temperature control (very critical; often ignored by many factories)
Initial mold preheating / first shot: 180–250°C. Never pour directly into a cold mold; rapid chilling of the molten aluminum causes cold shuts, and thermal shock can crack the mold.
Steady-state temperature in continuous production: 200–300°C.
- For thin-wall parts, use the upper limit, 250–300°C, to delay cooling of the molten aluminum.
- For thick-wall parts, use the lower limit, 200–240°C, to accelerate surface solidification of the casting and establish directional solidification (feeding from the far end of the casting toward the riser).
Mold temperature gradient: the temperature at the bottom / far end of the casting should be lower, while the temperature in the riser area should be higher, so as to achieve bottom-to-top directional solidification and reduce microshrinkage. Use mold insulating coatings, water cooling / air cooling, and heating rods for zoned temperature control.
Mold coatings: insulating coatings (risers / thin walls) and chill coatings (thick sections / hot spots) are used to locally adjust the cooling rate.
II. Pouring Speed (Filling Speed) Control
In gravity casting, faster is not always better. The goal is laminar filling: no turbulence or rolling, no splashing, molten aluminum rising smoothly, and air escaping smoothly through the vents.
Two expressions: ingate linear velocity (m/s) and total pouring time (s).
- Recommended ingate linear velocity
High-quality castings (valve bodies, seals, parts requiring T6 heat treatment): ≤0.5 m/s. This is commonly used in tilt-pouring gravity casting; the flow is laminar, the oxide film is hardly broken, and slag inclusions and gas porosity are greatly reduced. It is the golden threshold for high-end gravity-cast aluminum.
Ordinary housings and brackets: 0.5–0.8 m/s; try not to exceed 0.8 m/s for long periods, as this very easily causes air entrapment and oxide film entrainment, forming inclusion defects.
Direct top pouring: the drop height is large, so the flow velocity easily exceeds the limit. Tilt-pouring gravity casting is the optimal speed-control solution, with a small molten aluminum drop and uniform filling.
- Reference total pouring time (based on casting weight and cavity complexity)
- Small parts <1 kg: 5–10 s
- Medium castings 1–5 kg: 10–25 s
- Thick / complex parts above 5 kg: 20–40 s
Process debugging approach: start slowly, rise at a uniform speed, and slow down when nearly full. Rapid initial entry will cause the molten aluminum to impact the cavity bottom, splash, and break the oxide film.
- Speed control methods
Gating system design: ingate cross-section, pouring cup, and slag trap/weir; structurally limit the maximum flow velocity (most fundamental).
Equipment: tilting gravity casting machine (servo tilt-angle control, settable angular velocity, stable and repeatable); robotic ladling and pouring is much more consistent than manual ladling.
Manual pouring: fix the ladle height, maintain a stable ladle tilting angle, and keep a constant flow rate; keep the ladle spout always submerged below the molten aluminum surface (bottom-pour feeding to prevent air entrapment).
✅ Too fast: turbulence, splashing, air entrapment, oxidation inclusions, gas porosity.
✅ Too slow: premature solidification of molten aluminum → cold shuts, misruns.
III. Coupled Temperature + Speed Matching (Core of Process Debugging)
Thin-wall complex parts: higher temperature + moderate, slower filling speed, ensuring molten aluminum fluidity while avoiding air entrapment.
Thick, simple parts: lower temperature + low-speed smooth filling, reducing the risk of microshrinkage and hot tearing.
When the mold temperature is high, the pouring temperature can be appropriately lowered; when the mold temperature is low, the molten aluminum temperature should be raised to compensate.
Filling simulation (AnyCasting / ProCAST): predict flow velocity, air entrapment locations, and temperature field in advance to reduce trial cost.
IV. On-Site Monitoring and Stabilization Plan
Temperature measurement: furnace thermocouple + infrared temperature measurement at the gate; record the molten aluminum temperature for every shot. Use multi-point thermocouples in the mold to monitor mold temperature distribution.
Speed: the tilting machine records tilting time / angle; manual pouring uses fixed weight + timing.
Trial debugging sequence:
① First establish/fix the mold temperature gradient.
② Select the pouring temperature range.
③ Test pouring speed from slow to fast, and find the window with no air entrapment and no cold shuts.
Environment: when humidity is high, hydrogen absorption by molten aluminum intensifies; lower the upper limit of the pouring temperature.
V. Parameter Adjustments for Common Defects
Gas porosity / inclusions: reduce filling flow velocity, reduce molten aluminum drop height, lower pouring temperature, and strengthen degassing.
Cold shuts / misruns: increase molten aluminum temperature, increase mold temperature, and appropriately shorten pouring time.
Microshrinkage / shrinkage cavities: lower pouring temperature, optimize mold temperature gradient, and enhance riser insulation.
Hot cracks: lower pouring temperature, lower mold temperature, and reduce casting shrinkage stress.
